Customer |
Project |
Scope of services of NIIK |
Year |
|
LLC Zhilevskaya kremniorganika, Sitne-shchelkanovo, Moscow region, Russia | Ammonia-urea complex | Feasibility study | 2016 | |
Metafrax, Gubakha, Russia | Ammonia-urea-melamine complex | Reviewing options for site location, development of declaration of intention, preenvironmental impact assessment, participation in public hearings, detail design for site preparation, adaptation of Casale basic engineering package to Russian norms and regulations, authority package development, development of basic design for prilling tower , raw water treatment unit (including water intake unit) and waste water treatment system, equipment procurement for prilling tower construction. | 2015 - Under development | |
ShchekinoAzot, Shchekino, Russia | Methanol production unit | Reviewing options for unit location at ammonia, urea and supfuric acid production complex site |
2016 |
|
Haldor Topsoe (HTAS) |
Ammonia unit modernization aimed at capacity increase up to 2000 TPD at Uralchem site, Kirovo-Chepetsk, Kirov region |
1) Adaptation of HTAS design basis with the requirements of Russian Federation 2) Development of Authority Package including project's costs estimation 3) CO2 removal engineering package based on HTAS specification |
Under development |
|
ShchekinoAzot, Shchekino, Russia |
Ammonia-urea complex |
Development of declaration of intention |
Under development |
|
Sulphuric acid production plant and ammon-a- urea production complex at ShchekinoAzot site. |
Feasibility study to assess production site location |
2015 |
||
Grodno Azot, Grodno, Belarus |
Nitrogen complex (ammonia-urea-hydrogen) |
Feasibility study |
2015 |
|
Tulagiprohim, Tula, Russia |
Ammonia production unit, liquid ammonia storage unit for Ammonia Kingisepp Plant |
Basic design development for ammonia production plant: central control station, service- and- office building; for liquid ammonia storage facility: central station, laboratory, service- and- office building. |
2014-2015 |
|
Rosstroy, Novocherkassk, Russia |
Ammonia-urea complex |
Feasibility study |
2014 |
|
PhosAgro, Cherepovets, Russia |
Construction of ammonia production unit AM-3 (capacity 2200 TPD) |
Environmental Impact Assessment (front-end engineering stage), development of basic and detailed design (сivil engineering stage), harmonization of the documentation with the requirements of Russian Federation, field supervision |
2013 |
|
NevAzot (EuroChem), Nevinnomyssk, Russia |
Commercial grade aqua ammonia production unit for plant № 11 |
Basic and detailed design |
2013-2014 |
|
National Chemical Company, Russia |
Gaz -chemical complex (Kozmino, Primorsky territory) |
Declaration of intention development; Environmental Impact Assessment (front-end engineering stage); Declaration compliance with local codes, authority permits and approval; Participation in public hearings, customer support |
2013 |
|
ICM, Saint-Petersburg, Russia |
Ammonia – granulated urea complex based on natural gas, including utility corridor to port |
Declaration of intention development; BE and FEED stages technical support (harmonization of the documentation developed by foreign companies with the requirements of Russian Federation), environmental impact investigation (design basis stage), development of basic and detailed design |
2012-2014 |
|
Minudobreniya, Rossosh, Russia |
Ammonia-urea complex |
Feasibility study |
2012 |
|
Ammonia-Methanol- Urea complex (Tatarstan, Russia) |
||||
Mitsubishi Heavy Industries, Japan |
Architectural and civil documentation of urea production units and adjoining processing facilities |
Under development |
||
Ammoni, Mendeleevsk, Russia |
|
Harmonization of the documentation developed by foreign companies with the requirements of Russian Federation, equipment delivery, equipment certification (including foreign contractors equipment) |
Under development |
|
Ammoni, Mendeleevsk, Russia |
Ammonia- Methanol- Urea complex, Tatarstan, Russia Off- plant facilities construction (ammonia, urea, methanol, acid, alkalis storage units; loading/ unloading racks; waste-treatment facilities; demineralized water units, water recycling units, service- and- office buildings, substations, high- voltage transmission line (110 kW), automatic process control system, railroad, flare devices etc) |
Off plant facilities: turnkey construction projects including engineering, equipment delivery, construction and erection works, commissioning operations, operational documentation development, supervision etc. |
Under development |
|
ShchekinoAzot, Shchekino, Russia |
Ammonia-urea complex |
Feasibility study |
2011 |
|
Ammoni, Mendeleevsk, Russia |
Ammonia-methanol-urea chemical complex |
Development of basic design for urea plant. |
2008–2009 |
|
Diagnostics of HP urea equipment and pipelines. Repair of urea production equipment |
||||
Grodno Azot, Grodno, Belarus |
Inspection of absorber ferromagnetic heat exchanger tubes (ammonia plant № 4) |
Inspection of heat- exchanger tubes by eddy-current method, visual inspection |
2013 |
|
Azot, Cherkassy, Ukraine |
Ferromagnetic heat- exchanger tubes inspection (pos. 1140-C, ammonia plant A-5) |
Inspection of heat- exchanger tubes by eddy-current method, visual inspection |
2012 |
Urea and other products storage units |
|||
Balakovo Mineral Fertilisers, Balakovo, Russia |
Grass-root above-ground ammonia storage unit |
Feasibility study according to alternative variants |
2010 |
Other works |
|||
AutoVAZ, Togliatti, Russia |
Technical upgrading of liquid ammonia evaporation unit |
Development of basic and detailed design, industrial safety expertise, development of emergency localization plans and adjustment of current regulations |
2010 |