NIIK will develop basic and detailed design for the new urea granulation unit with capacity 1500 TPD for PhosAgro-Cherepovets.
03/26/2015
The construction of a new urea granulation unit with capacity 1500 TPD is only a part of a comprehensive development concept.
NIIK signed an agreement and started evaluation of the potential of a new project in Grodno (Belarus)
03/25/2015
As part of feasibility studies NIIK will select the optimal technology, main equipment, units and engineering infrastructure. Based on NIIK investigation Council of Ministers of the Republic of Belarus will take a decision on the complex construction.
Nitrogen & Syngas 2015
03/10/2015
Nitrogen & Syngas 2015.
NIIK delegation presented by Chairman of the Board Igor Esin, General Director Oleg Kostin, Dy. General Director for R&D Nikolay Lobanov, Head of Corrosion Department Alexander Chirkov, Head of Group of Process Department Alexander Vorobev, Head of International Affairs Department Natalia Kargaeva, International Affairs Manager Alexey Andreev attended Conference and Exhibition Nitrogen & Syngas 2015 that took place on 23-26 February in Istanbul, Turkey.
NIIK delegation presented by Chairman of the Board Igor Esin, General Director Oleg Kostin, Dy. General Director for R&D Nikolay Lobanov, Head of Corrosion Department Alexander Chirkov, Head of Group of Process Department Alexander Vorobev, Head of International Affairs Department Natalia Kargaeva, International Affairs Manager Alexey Andreev attended Conference and Exhibition Nitrogen & Syngas 2015 that took place on 23-26 February in Istanbul, Turkey.
During 3-5 February 2015 NIIK’s delegation took part in the 21st International Annual Fertilizer Forum, organized by Arab Fertilizer Association (AFA) in Hurghada, Egypt
02/13/2015
The delegation was represented by Deputy General Director for R&D Nikolay Lobanov, Head of corrosion, welding and diagnostics department Alexander Chirkov, Head of Process Department Rinat Anderzhanov and International Affairs Manager Dmitry Obedin.
Authority design package developed by NIIK for PhosAgro- Cherepovets ammonia production unit (capacity 2200 TPD) was approved by GlavGosExpertise.
12/27/2014
NIIK is taking part in the construction project for a new ammonia plant in the Vologda region. The new line is expected to have an ammonia production capacity of 2,200 TPD, 760 ths TPY (Haldor Topsoe license). The project is being realized by PhosAgro- Cherepovets company which signed a contract with an international consortium led by Mitsubishi Heavy Industries.