Current references

Video Видео
Our Listings


Customer

Project

Scope of services of NIIK

Year

EPC/Turnkey projects

Metafrax, Gubakha, Russia

Ammonia-urea-melamine complex

- Сonstruction of OSBL facilities on a turn- key basis (basic and detail design, equipment procurement, assembly&installation, start- up & commissioning)

2016 to present

PhosAgro, Cherepovets, Russia

Mitsubishi Heavy Industries, Japan

Ammonia production unit AM-3 (capacity 2200 TPD)

- Turn-key project for construction of a new analytical laboratory (ammonia production plant)

2016-2017

Ammoni, Mendeleevsk, Tatarstan, Russia

Ammonia-methanol-urea complex

- Сonstruction of OSBL facilities on a turn- key basis (basic and detail design, equipment procurement, assembly&installation, start- up & commissioning)

2010-2015

Zawolzhsky Motorny Zawod, Zavolshye, Russia

Construction of testing station for diesel engines

- Turnkey project

2009

Zawolzhsky Motorny Zawod, Zavolshye, Russia

Revamp of sulphuric acid storage unit

- Turnkey project

2006-2007

Petrol storage unit

- Turnkey project

2006

Nizhegorodsky machine-building plant, Russia

Revamping of chlorine storage unit and chlorinator

- Turnkey project

2006-2007

Design engineering

Production complexes

Not disclosed (Confidential Information) Ammonia-urea- complex - Adaptation of licenser’s basic engineering package to Russian norms and regulations 2020
UCC Shchekinoazot Ltd., Schekino, Russia
China National Chemical Engineering Co. (CNCEC), Ltd., China
Urea-Ammonia Complex - Adaptation of the Basic Projects of the Licensors to the norms and rules of the Russian Federation
- Design documentation for the complex (ISBL / OSBL objects)
2019 - 2021
- Adaptation of Working Documentation developed by CNCEC to the norms and rules of the Russian Federation Under development
Metafrax, Gubakha, Russia, Casale S.A., Switzerland Ammonia-urea-melamine complex - Basic design for OSBL facilities (Melamine 2 unit)
- Revision of basic design for prilling tower with capacity 1150 TPD

2018 to present

Metafrax, Gubakha, Russia

Ammonia-urea-melamine complex

- Development of detail design for site arrangement

- Adaptation of licenser’s basic engineering package to Russian norms and regulations

- Authority package development (ISBL/OSBL)

- Construction of OSBL facilities on a turn-key basis (detail design, equipment procurement, assembly& installation, start-up&comissioning)

2016 to present

Metafrax, Gubakha, Russia

Casale S.A.,

Switzerland

Ammonia-urea-melamine complex

- Development of basic design for OSBL facilities and prilling tower

- Detail design (ISBL facilities’ architectural and civil documentation)

Ammoni,

Mendeleevsk,

Tatarstan,

Russia

Ammonia-methanol-urea complex

- Development of authority package (ISBL/OSBL)

- Сonstruction of OSBL

facilities on a turn- key basis (detail design, equipment procurement, assembly&installation, start- up & commissioning)

2010-2015

Ammoni,

Mendeleevsk,

Tatarstan,

Russia

Mitsubishi Heavy Industries, Ltd. (MHI), Japan

Ammonia-methanol-urea complex

- Adaptation of licenser’s documentation on ISBL facilities to Russian norms and regulations,

- Detail design (architectural and civil documentation for urea production ISBL facilities)

- Licenser’s equipment certification

ICM,

Saint-Petersburg,

Russia

Ammonia –urea complex (Vistino, Kingisepp, Leningrad region)

- Adaptation of BE/FEED licensor’s documentation to Russian norms and Regulations

- Development of authority package (ISBL/OSBL)

2013-2015

Ammonia production units

Geammarco Vetrocoke Srl, Italy

CO2 removal system modernization (ammonium production unit designed by TEC) aimed at capacity increase up to 2000 TPD at Perm mineral fertilizer site.

- - Authority package development

- Development of authority package including documentation for CO2 removal unit

2018 - 2019

Haldor Topsoe (HTAS), Denmark

Ammonia unit modernization aimed at capacity increase up to 2000 TPD at Uralchem site (Kirovo-Chepetsk, Kirov region)

- Adaptation of design basis to Russian norms and regulations

- Development of authority package including documentation for CO2 removal unit

2015 -2017

Tulagiprohim,

Tula,

Russia

Ammonia production unit and liquid ammonia storage unit (Kingisepp Plant)

- Development of authority package for OSBL facilities

2014-2015

PhosAgro,

Cherepovets,

Russia

Ammonia production unit AM-3 (capacity 2200 TPD)

- Adaptation of licenser’s basic engineering package to Russian norms and regulations

- Development of

basic and detailed

design

2013-2017

PhosAgro,

Cherepovets,

Russia

Mitsubishi Heavy Industries,

Japan

Ammonia production unit AM-3 (capacity 2200 TPD)

- Detail design

(architectural and

civil documentation)

- Turn-key project for construction of a new analytical laboratory (ammonia production plant)

2014-2017

2016-2017

Not disclosed

(Confidential Information)

Ammonia production unit

- Adaptation of licenser’s basic engineering package to Russian norms and regulations

- Authority package development

Detail design development

2013-2017

EuroChem, NevAzot, Nevinnomyssk,

Russia

Commercial grade aqua ammonia production unit (plant №11)

- Authority package development

- Detail design development

2013-2014

Not disclosed (Confidential Information) Methanol production unit - Adaptation of the Licensor's FEED package to the rules and regulations of the Russian Federation
- Development of FEED parts in the scope of the construction part and the HVAC system
- Project documentation
2020-2021
OOO «G T M 1», Volgograd, Russia Methanol production - Adaptation of the Licensor's FEED package to the rules and regulations of the Russian Federation
- Project documentation
Under development
Metafrax, Gubaha, Russia Technical modernization of methanol production unit (integration within an ammonia-methanol-urea complex) - Detailed design development Under development
Technolizing, Skovorodino, Russia Methanol production unit with capacity 3000 TPD Adaptation of licenser’s basic engineering package to Russian norms and regulations

2018 – 2020

Engineering research assistance

Under development

Engineering&Consulting services on organizational issues related to public hearings

2021

Nizhnekamskneftekhim, Nizhnekamsk, Tatarstan Methanol production with capacity 500 000 TPY - Authority package development
- Detailed design development
- Field supervision

Under development

Metafrax, Gubaha, Russia, Casale SA, Switzerland Methanol production unit modernization including integration to ammonia-urea-methanol complex - Adaptation of licenser’s basic engineering package to Russian norms and regulations
- Detailed design of civil part

2018 to present

ShchekinoAzot, Shchekino, Russia Methanol production unit with capacity 500 000 TPY - Adaptation of licenser’s basic engineering package to Russian norms and regulations
- Authority package development
- Detail design development

2018 – 2021

- Field supervision

Under development

Baltic Gas Chemical Company, Saint-Petersburg, Russia

Baltic methanol production plant

- Adaptation of licenser’s basic engineering package to Russian norms and regulations

- Authority Package development

- Detail design development

2015 – to present

Urea production units

Not specified under the terms of confidentiality Technical re-equipment of the synthesis column for urea production Working documentation 2020 - 2021
JSC Nevinnomyssky Azot, Nevinnomyssk, Russia (EuroChem Group AG) Technical re-equipment of the evaporation unit of workshop No. 2-a of urea production Working documentation 2020 - 2021
ООО “Novomoskovsk-Remstroiservis”, Novomoskovsk, Russia Modernization of the pre-decomposition unit pos. 11-E-2A in the urea plant No. 3 (stage 1) of NAK Azot JSC Working documentation 2020
Not disclosed (Confidential Information) Urea production unit - Detail design development (civil, electrical, HVAC sections)
- Adaptation of detail design to Russian norms and regulations
Under development
KuibyshevAzot, Togliatti, Russia Technical modernization of urea plant №4 - Authority Package development
- Detail design development

2018 - 2019

Novgorodsky GIAP, Veliky Novgorod,

Russia

Urea unit № 6 modernization aimed at capacity increase to 2050 TPD (Acron site) - Main technical solutions development
- Authority Package development
- Detail design development

2021

Urea granulation unit with capacity 2000 TPD (Acron site) - Authority Package development
- Detail design development

2018 to present

New urea production unit №6 with capacity 600 TPD (Acron site)

- Authority Package

development

- Detail design

development

2018

Urea unit №5 modernization aimed at capacity increase to 1250 TPD (Acron site)

- Authority Package

development

- Detail design

development

2017

KuibyshevAzot, Togliatti, Russia

Stamicarbon,

The Netherlands

Urea production unit with capacity 1500 TPD (at KuibyshevAzot site)

- Adaptation of licenser’s documentation on ISBL facilities to Russian norms and regulations,

- Basic design for urea production OSBL facilities

- Authority Package development

2017 - 2019

KuibyshevAzot, Togliatti, Russia

Technical modernization of urea unit № 4 (evaporation, hydrolysis and desorption sections)

- Detail design development

2016-2017

Minudobreniya, Perm,

Russia

Stamicarbon,

The Netherlands

Urea production unit modernization aimed at capacity increase to 2700 TPD, new prilling tower construction

- Adaptation of licenser’s basic engineering package to Russian norms and regulations,

- Basic design documentation development for prilling tower

- Authority package development

2015-2019

Minudobreniya, Perm, Russia Urea production unit modernization aimed at capacity increase to 2700 TPD, new prilling tower construction - Detail design development

2015 - 2019

Togliattiazot, Togliatti, Samara, Russia

Urea production unit and new prilling tower construction (capacity 2200 TPD) at TogliattyAzot site

Adaptation of licenser’s basic engineering package to Russian norms and regulations

2015- 2016

Authority package development (including prilling tower and handling system).

2019

Detailed design development

2020

Field supervision

Under development

PhosAgro- Cherepovets, Cherepovets,

Russia

Urea granulation unit, capacity 1500 TPD

- Authority package development

- Detailed design development

2014-2017

Technical modernization of urea production unit № 2 aimed at capacity increase to 1650 TPD

- Authority package

development

- Detailed design

development

2014-2016

EuroChem,

NAK Azot,

Novomoskovsk,

Russia

Technical modernization of urea production unit № 2 aimed at capacity increase to 1500 TPD

- Authority package

development

- Detailed design

development

2013-2017

Technical modernization of urea plant № 3 (second line) with capacity increase to 1450 TPD

- Authority package

development

- Detailed design

development

2013-2016

UAN production unit on the basis of urea production plant № 2 (capacity 1200 TPD)

- Authority package

development

- Detailed design

development

2013-2014

Revamp of urea unit №2 (gas vent elimination)

- Authority package

development

- Detailed design

development

2012-2015

32,5% urea solution production unit (capacity 100000 TPY) including urea solution treatment unit on the basis of urea plant № 2 evaporation unit

- Authority package

development

- Detailed design

development

2011-2015

Chemoproject,

Czech Republic

AZOMURES S.A. plant' s prilling tower modernization aimed to capacity increase from 900 to 1425 TPD, keeping the tower´s height and ensuring the same quality level.

- Acting as general design contractor

- Development of technical solutions

2012

Acron, Veliky Novgorod, Russia

Urea production units (№1-4) revamping aimed to capacity increase up to 2000 TPD and feedstock / energy saving

- Authority package

development

- Detailed design development

2009-
2016

Urea synthesis unit revamp (№5)

- Authority package

development

- Detailed design development

2013-2014

Azot,

Kemerovo,

Russia

Urea production unit revamp with high speed drum granulator installation

- Authority package

Development

- Detailed design development

2011-2013

Kuibyshev Azot,

Togliatti,

Russia

Acid ammonia recovery unit downstream urea unit absorption tower

- Authority package

Development

- Detailed design development

2011-2012

EuroChem,

NAK Azot,

Novomoskovsk,

Russia

Technical modernization of evaporation unit № 5 for urea production unit №2 (capacity 1000 TPD)

- Authority package

Development

- Detailed design development

2011-2012

Acron,

Veliky Novgorod,

Russia

Implementation of computer process simulator for personal training and knowledge assessment

- Computer-generated technological simulator for urea production assembly №5

2011-2012

Evaporation system for urea production unit and prilling tower modernization with capacity increase

- Detailed design development

2011-2013

Maxam-Chirchik,

Chirchik,

Uzbekistan

Modernization and technical upgrading of urea unit

- Authority package

Development

- Detailed design development

2010-2012

EuroChem, NevAzot, Nevinnomyssk,

Russia

Modernization of unit №2 (urea plant №2)

- Authority package

Development

- Detailed design development

2010-2011

EuroChem, NAK Azot, Novomoskovsk,

Russia

Implementation of computer process simulator for personnel training and knowledge assessment

- Hard- and software complex

2010 – 2011

PhosAgro,

Cherepovets,

Russia

Urea plant production unit with capacity 1500 TPD, procured by “Chemoproject” (Czech Republic)

- Authority package

Development

- Detailed design development

2010-

2012

Design Institute «Salavatgasonephte-himproect»,

Salavat, Republic of Bashkortostan,

Russia

Prilling tower for urea plant №24

- Adaptation of licenser’s basic

engineering package

(“TEC”, Japan) to

Russian norms and

regulations

- Authority package

development

- Detailed design development

2010-

2011

PhosAgro,

Cherepovets,

Russia

Implementation of computer process simulator for personnel training and knowledge assessment

- Hard- and software complex

2010-

2011

Revamp of urea synthesis evaporation unit

- Authority package

development

- Detailed design development

2010

Kuibyshev Azot, Togliatti, Russia

Prilling tower revamp (urea plant №4)

- Detailed design development

2010

Revamp of evaporation unit (urea plant №1, unit № 4)

- Detailed design

development

2010

Salavatnefteorgsintez

Salavat, Russia

Prilling towers revamp (urea plant №24)

- Authority package

development

- Detailed design

development

2009-2010

Yokogawa Electric,

Moscow

Development of control system for CO2 compressor with arrangement of a room for a set of technical devices at NAK “Azot"

- Detailed design

development

2009

Acron, Veliky Novgorod, Russia

Design of granulated urea unit based on Rotoform technology

- Detailed design

development

2009

PhosAgro AG - Cherepovetsky Azot, Cherepovets, Russia

Urea production unit with capacity 1500 TPD, procured by “Chemoproject” (Czech Republic)

- Authority package

development

- Detailed design

development

2008 – 2012

Togliattiazot,

Togliatti, Samara, Russia

Prilling tower modernization (urea plant)

- Detailed design

development

2008-2009

Acron, Veliky Novgorod, Russia

Urea unit revamp with capacity increase and energy saving

- Authority package

development

- Detailed design

development

2008

UralChem,

Voskresensk Mineral Fertilizers, Voskresensk, Russia

Urea production unit with capacity 600 (1200) TPD

- Authority package

development

2008

Acron,

Veliky Novgorod,

Russia

Urea unit №5 on the basis of relocated unit

- Authority package

development

- Detailed design

development

2007 – 2011

EuroChem, NevAzot, Nevinnomyssk,

Russia

Prilling tower revamp (urea unit, plant 2A)

- Authority package

development

- Design documentation development

2007-2009

Grodno Azot, Grodno, Belarus

Revamp of urea plant №4 with capacity increase

- Feasibility study,

- Architectural and civil design

2007 – 2012

EuroChem,

NAK Azot, Novomoskovsk,

Russia

Urea production unit on the basis of relocatable unit with capacity increase and energy saving

- Authority package

development

- Detailed design

development

2007– 2010

Revamp of urea plant №3 with capacity increase to 2000 TPD

- Authority package

development

- Detailed design

development

2007 – 2010

Severodonetsk Azot Association, Severodonetsk, Ukraine

Development of basic design for urea unit revamp with capacity increase from 1200 up to 1500 TPD

- Authority package

development

- Detailed design

development

2007 – 2010

EuroChem, NevAzot ,

Nevinnomyssk,

Russia

Urea evaporation unit for melamine plant

- Authority package

development

- Detailed design

development

2008 – 2010

TogliattiAzot,

Togliatti,

Russia

Technical upgrading of urea unit with integration of melamine unit

- Authority package

development

2007 – 2008

KuibyshevAzot,

Togliatti,

Russia

Revamp of urea unit with capacity increase

- Authority package

development

- Detailed design

development

2007 – 2008

Salavatnefteorgsintez

Salavat, Russia

Basic design for urea prilling tower

- Authority package

development

- Detailed design

development

2007-2008

Severodonetsk Azot Association,

Severodonetsk,

Ukraine

Development of basic design for urea unit revamp with capacity increase from 1000 up to 1200 TPD

- Authority package

development

- Detailed design

development

2006-2007

AB Achema,

Lithuania

Urea production unit based on relocatable equipment

- Authority package development

- Detailed design development

- Development of operational manuals

2006-2008

PhosAgro,

Cherepovets,

Russia

Revamping of distillation unit with capacity increase (urea production plant)

- Authority package development

- Detailed design development

2007

EuroChem,

NAK Azot, Novomoskovsk,

Russia

Implementation of computer process simulator for personnel training and knowledge assessment

- Hard- and software complex

2006-2008

Ostchem Group,

Azot, Cherkassy,

Ukraine

Revamping of urea unit М-6

- Authority package development

- Detailed design development

2006-2010

Salavatnefteorgsintez,

Salavat, Russia

Revamping of urea plant №50

- Authority package development

- Detailed design development

2006 – 2008

Fertalge Industries SPA,

Algeria

Prilling tower for urea production

- Authority package development

- Detailed design

development

2006-2008

Dorogobuzh, Verkhnedneprovsky, Smolensk region,

Russia

Urea production unit based on relocatable equipment, urea storage unit, prilling tower

- Authority package development

2006 - 2007

Grodno Azot, Grodno, Belarus

Revamp of urea production unit, installation of recuperator

- Detailed design

development

2006

Acron,

Veliky Novgorod,

Russia

Installation of the 5th urea synthesis reactor

- Detailed design

development

2006

NevAzot,

Nevinnomyssk,

Russia

Revamp of urea production unit №2

- Authority package

development

- Detailed design

development

2006

Melamine production

EuroChem, NevAzot, Nevinnomyssk,

Russia

Melamine unit by LURGI AG technology, Germany

- Authority package based on foreign licensor’s basic engineering package

- Detailed design of architectural and civil part

2007 – 2011

TogliattiAzot,

Togliatti,

Russia

Technical upgrading of urea unit with integration of melamine unit

- Authority package development

2007 – 2008

Acron, Veliky Novgorod, Russia

Melamine production unit

- Feasibility study

- Environmental impact investigation

2006 – 2007

Hydrogen production

Shchekinoazot,

Shchekino,

Russia

Hydrogen recovery unit

- Acting as general design contractor

- Authority package

development based on foreign licensor’s basic engineering package

- Detailed design

development

2010-2011

Ammonium nitrate production

NIUIF, Cherepovets, Russia High speed drum granulation unit for urea and ammonium nitrate based fertilizers production - Technical solutions development

2018-2019

TomskAzot,
Seversk, Тomskiy region, Russia

Modernization of the existing Drum Granulation unit to shift it to the production of the granulated ammonium nitrate.

- Design documentation development

2017

KazAzot,

Aktau,

Kazakhstan

Ammonia nitrate production unit modernization: HSDG for ammonia nitrate manufacturing

- Technical solution development

- Detail design development

2011-2012

Other production

Not specified under the terms of confidentiality AGCC - Authority package development 2021 to present
Not specified under the terms of confidentiality AGCC - Detailed design development 2021 to present
Not specified under the terms of confidentiality AGCC - Authority package development
- Detailed design in part of plot plan & external water supply and water disposal system
2020 to present
Not specified under the terms of confidentiality AGCC - Authority package development 2020 - 2021
Not specified under the terms of confidentiality AGCC - Authority package development 2020 - 2021
Not specified under the terms of confidentiality AGCC - Authority package development 2020 - 2021
Not specified under the terms of confidentiality Reconstruction of the gas supply network - Authority package development 2021
Not disclosed (Confidential Information) Gas treatment plant (OSBL facilities, household building with canteen) - Authority package development 2020 to present
Gas treatment plant (OSBL facilities, fire station & gas rescue service) - Authority package development 2020 to present
Gas treatment plant (intershop racks) - Authority package development 2020 to present
Not disclosed (Confidential Information) Installation of the hydro foamy filtration system (wet scrubbing) - Detail design development
- Field supervision
- Technical assistance during commissioning
2020
UralChem, Berezniki, Russia Technical modernization of nitrate- nitrite salt production unit (building 449) - Technical solution development
- Basic Engineering Design

2018-2019

Volzhskiy Orgsintez- Volzhsky, Volgograd region,

Russia

Sodium dimetilditiocarbamate production unit, capacity 15000 tons per year - Adaptation of licenser’s (EPC) detailed design

2018 - 2019

Sodium dimetilditiocarbamate production unit, capacity 15000 tons per year

- Authority package development

- Detailed design

development

2017-2018

FCE plant named after Sverdlov Dzerzhinsk, Nizhny Novgorod region, Russia Modernization aimed at construction of a small-scale hexogen production unit (using technology № 2.1.6.100) - Construction design supervision

2018

Technical modernization providing production process mechanization and automation - Construction design supervision 2018-2019
Salavat Neftekhimremstroy, Salavat, Russia Development of detailed design for additional heating equipment U-EA 602, U-EA 603, U-EA 604 based on technical documentation M/DK-14-169.00.00.BO. Development of design and estimate documentation for steam tracing change. - Detailed design development
- Estimate documentation
- Field supervision

2018

Korund-Cyan,

Dzerzhinsk,

Russia

Sodium cyanide production unit modernization& construction (second stage: additional engineering system monitoring) - Detail design development 2018-2019
Sodium cyanide production unit modernization. Additional equipment installation (buildings B60, B40) - Adaptation of licenser’s (EPC) detailed design 2018-2019
Modernization and construction of railway tracks - Authority package development
- Detailed design development
2018 - 2019
 Modernization of administrative and service building A 13 - Authority package development

- Detailed design development

 2017
Testing the feasibility of repairing furnace lining  (building B70)   - Detailed design development  2017
Technical modernization of the cooling water unit (Sodium cyanide production unit, building В50)

- Authority package development

- Detailed design

development

2016-2017

Sodium cyanide production unit modernization& construction - Detailed design development

2016

Alcali storage unit modernization (sodium cyanide production unit, building B80)

- Authority package development

- Detailed design

development

2016

Sodium cyanide storage unit technical modernization

- Detailed design

development

2015

Sodium cyanide production unit with capacity of 80000 TPD (first and second line)

- Acting as general design contractor

- Authority package

development based on foreign licensor’s basic engineering package (EPC, Germany)

- Detailed design

development

2010-2012

SNF Flopam

Qatar

Acrylamide and polyacrylamide production unit with capacity of 60 000 TPY - Authority package development 2017

QAFCO (Qatar Fertilizer Company),

Qatar

Multipurpose High Speed Drum Granulation (HSDG) Pilot Plant for production of granulated urea with additives, capacity 100 kg per hour

- Technology licensing

- Engineering

2014-2015

PVFCCо,

Phu My I,

Ba Ria Vung Tau,

Vietnam

High Speed Drum Granulation unit for production of compound fertilizers (capacity 100 kg/h)

- Technology licensing

- Engineering

2014-2015

Kuibyshev Azot,

Togliatti,

Russia

Implementation of catalytic purification system, compressor plant, outdoor installations and production buildings (energy efficient cyclohexanol production unit installation project, capacity 140000 TPY)

- Authority package development

- Detailed design

development

2012-2014

Nizhfarm,

Nizhny Novgorod,

Russia

Grass-root gel production plant

- Adaptation of licenser’s basic engineering package (“Chemofarm engineering”, Belgrad, Serbia) to Russian norms and regulations

2011

Zawolzhsky Motorny Zawod,

Zavolshye, Russia

Technical upgrading of pipelines for acids solution discharge in heat-treating workshop

- Detailed design development

2011

TIKO-Plastic,

Dzerzhinsk,

Russia

Expanding capacity of plastic film production plant. Production building construction

- Acting as general design contractor

- Authority package development

- Detail design development (architectural and civil documentation)

2010-2011

Nexis,

Perm,

Russia

CAN (capacity 10 000 TPY) and magnesium nitrate production units (solid or liquid form)

- Development of initial data for design works

- Development of design documentation for nonstandardized equipment

2010

AutoVAZ,

Togliatti,

Russia

Technical upgrading of liquid ammonia evaporation unit

- Authority package development

- Detailed design

development

- Adaptation of technical rules to current regulations

2010

Zawolzhsky Motorny Zawod, Zavolshye,

Russia

Construction of testing station for diesel engines

- Turnkey project

2009

Korund,

Dzerzhinsk,

Russia

Lacquer, paint and polyester resins production unit

- Acting as general design contractor

- Detailed design

development (infrastructure)

2005-2007

Storage units

Metafrax,

Gubaha,

Russia

Revamp of urea storage unit unloading section

- Authority package development

- Detailed design

development

2013

Korund, Dzerzhinsk,

Russia

Revamp of chlorine storage unit, adaptation to industry safety requirements

- Detailed design

development

2009

Ammoni,

Mendeleevsk,

Russia

Construction of urea storage complex

- Basic design

2008 – 2009

Pervouralsky novotrubny works, Perovuralsk,

Russia

Revamp of liquid ammonia storage unit № 33

- Authority package development

- Detailed design

development

2006-2007

Zawolzhsky Motorny Zawod,

Zavolshye,

Russia

Revamp of sulphuric acid storage unit

- Turnkey project

2006-2007

Petrol storage unit

- Turnkey project

2006

Nizhegorodsky machine-building plant,

Russia

Revamping of chlorine storage unit and chlorinator

- Turnkey project

2006-2007

Kuibyshev Azot, Togliatti, Russia

Revamping of urea storage unit

- Authority package development

- Detailed design

development

2007

TIKO-Plastic,

Dzerzhinsk,

Russia

Feedstock and final product storage facilities

- Authority package development

- Detailed design

development

2006

Pre-design services

Not disclosed (Confidential information) Urea production - Investment feasibility study Under development
Apatite, Cherepovets, Russia Ammonia production - Consulting services on effective facility arrangement, estimation of the project cost 2019-2020
Not disclosed (Сonfidential information) Ammonia- methanol- urea\other nitrogen products complex - Front-end engineering (detailed estimation of overall scope, reviewing options for site location)2019-2020
Not disclosed (Сonfidential information) Ammonia- methanol- urea complex - Front- end engineering (developing options for different construction sites) 2019
Not disclosed (Сonfidential information) Methanol production complex in extreme conditions of the Far North - Investment feasibility study
- Declaration of intention development
2019
Not disclosed (Сonfidential information) Ammonia- urea production complex - Feasibility study
- Environmental impact assessment
2018
«Meleuz mineral fertilizers», Meleuz, Russia Methanol production complex - Investment feasibility study
- Declaration of intention development
2019
«Meleuz mineral fertilizers», Meleuz, Russia Repair of UKL-7-76 №2 for ammonium nitrate production and shipment. Capacity 450 000 TPY Investment feasibility studyUnder development
Askom Methanol production with capacity 2 500 TPD - Investment feasibility study2018
Kazphosphate, Kazakhstan Ammonia production with capacity 1 000 000 TPY - Investment feasibility studyUnder development
KazAzot, Aktau, Kazakhstan Ammonia\urea and (or) natural gas deep processing products production complex- Investment feasibility study2017
Novgorodsky GIAP, Veliky Novgorod, Russia Ammonia and urea production complex (Dorogobuzh site)- Feasibility study2017
Yakut gas processing complex, Saha, Yakutsk, Russia Preliminary planning and engineering at feasibility study stage (Methanol production unit with capacity 10000 TPD) - Preconstruction surveys2017
Development of environmental impact assessment reports - Environmental impact assessment Assisting with ecological expertize approval 2017
Not disclosed (Confidential Information) Methanol production - Feasibility study2017

Amec Foster Wheeler,
Moscow, Russia

Methanol production unit with capacity 10000 TPD for Yakut Fuel and Energy Company

- Investment feasibility study

Under development

Not disclosed

(Confidential Information)

Methanol production unit

- Investment feasibility study

2017

Baltic Gas Chemical Company, Saint-Petersburg, Russia

M-15 production unit with capacity 15000 TPY for Chayandinskoye field.

- Development of declaration of intention

2017

CREON-ENERGY,

Moscow,

Russia

Methanol production unit with capacity 1mln TPY (Novoroscement site)

- Methanol production unit tie- up for site infrastructure

2017

Jugterminalproect,

Moscow, Russia

Methanol- Ammonia- Urea complex (Taman region)

- Front-end engineering design

2017

Azot,

Kemerovo,

Russia

UAN production unit with capacity 150000 TPD

- Investment feasibility study

2017

Teсhnoleasing,

Moscow,

Russia

Methanol production unit (Skovorodino, Amur region)

- Investment feasibility study

2017

Novgorodsky GIAP, Veliky Novgorod,

Russia

- Sulfuric acid production unit

- Wet-process phosphoric acid production unit

- Monoammonium phosphate (MAP) and\or diammonium phosphate (DAP) production unit

- Investment feasibility study

2016

Metafrax, Gubakha, Russia

Ammonia-urea-melamine complex

- Reviewing options for site location

- Development of declaration of intention

- Environmental impact assessment

- Conducting public hearings

2015 -2016

OJSC MMC Norilsk Nickel, Moscow, Russia

Urea production complex (Dudinka site)

- Investment feasibility study

2016

LLC Zhilevskaya kremniorganika, Sitne-shchelkanovo, Moscow region, Russia

Ammonia-urea complex

- Investment feasibility study

2016

ShchekinoAzot,

Shchekino,

Russia

Methanol production unit with capacity 500000 TPY

- Reviewing options for methanol unit location at ShchekinoAzot site

2016

Ammonia-urea complex

- Development of declaration of intention

2016

Sulphuric acid production unit construction

- Site location estimation

2015

Grodno Azot, Grodno, Belarus

Nitrogen complex (ammonia-urea-hydrogen)

- Investment feasibility study

2015

KuibyshevAzot, Togliatti, Russia

Urea production unit

- Investment feasibility study

2014

Sibmetahim,

Tomsk,

Russia

Chemicals manufacturing unit (synthetic fluid \ ammonia-urea melamine complex)

- Expert economic assessment

2014

CREON-ENERGY,

Moscow,

Russia

Methanol production with capacity 5000 TPD (Ust-Luga region)

- Investment feasibility study

2014

Rosstroy,
Novocherkassk, Russia

Ammonia-urea complex

- Investment feasibility study

2014

PhosAgro,

Cherepovets,

Russia

Granulated urea production unit with capacity 1500 TPD

- Pre-feasibility study

2014

Ammonia production unit AM-3 (capacity 2200 TPD)

- Pre-feasibility study

2013- 2014

National Chemical Company, Russia

Gaz -chemical complex (Kozmino, Primorsky territory)

- Declaration of intention development

- Environmental Impact assessment

- Conducting public hearings

2013

ICM,

Saint-Petersburg,

Russia

Ammonia –urea complex (Kingisepp region, Leningrad region)

- Declaration of intention development

- Environmental impact assessment

2012-2013

Minudobreniya, Rossosh, Russia

Ammonia-urea complex

- Investment feasibility study

2012

ShchekinoAzot,

Shchekino,

Russia

Ammonia-urea complex

- Investment feasibility study

2010- 2011

Hydrogen production unit

- Investment feasibility study

2011

Balakovo Mineral Fertilisers (PhosAgro),

Balakovo,

Russia

Above-ground ammonia storage unit

- Investment feasibility study

2010

Technical assessment & inspection services

EuroChem, NevAzot, Nevinnomyssk, Russia Urea production unit 2A inspection to improve synthesis unit efficiency when operating urea unit and melamine production facility jointly - Technical inspection 2019
Maxam-Chirchik, Chirchik, Uzbekistan Urea production unit inspection to develop options to reduce emissions and minimize the amount of effluents - Technical inspection
2019
EuroChem, NAK Azot, Novomoskovsk, Russia Technical inspection of evaporation unit (urea plant № 2) - Technical inspection
- Issuing recommendations
2019
Maxam-Chirchik, Chirchik, Uzbekistan Technical inspection of nitric acid production units АК-72М\АК-72 - Technical inspection 2019
PMU, UralChem, Perm, Russia Certification of measurement procedures - Evaluation and confirmation of compliance of measurement procedures with the established requirements
- Modifying measurement procedures to bring them in line with the requirements
2018
Grodno Azot, Grodno, Belarus Complex inspection of Urea 3 plant- Technical inspection 2018
TechnoChimReagentBel, Grodno, Belarus Certification of measurement procedures- Evaluation and confirmation of compliance of measurement procedures with the established requirements
- Modifying measurement procedures to bring them in line with the requirements
2018
Certification of measurement procedures- Evaluation and confirmation of compliance of measurement procedures with the established requirements
- Modifying measurement procedures to bring them in line with the requirements
2017
Union of producers and consumers of automobile chemical goods, Moscow, Russia Certification of measurement procedures- Evaluation and confirmation of compliance of measurement procedures with the established requirements
- Modifying measurement procedures to bring them in line with the established requirements
 2017
PhosAgro, Cherepovets, Russia Revision of existing operating procedures (urea production units № 1 and №2)Making amendments to the operating procedures 2017
Salavatnefteorgsintez Salavat, Russia Field supervision and technical support during construction and commissioning (modernization of urea production unit №24 granulation section, capacity 1400 TPD)- Field supervision
- Technical support during construction
- Commissioning
 2017

Gasprombank,
Moscow,
Azot,
Kemerovo,
Russia

Technical inspection of SDS- Azot urea production facilities

- Equipment & urea production process condition assessment, development of engineering solutions optimizing technological processes, reducing energy consumption and enhancing reliability of unit operation.

2017

Grodno Azot, Grodno, Belarus

Development of technical solutions for distillation gases treatment unit (urea plant №2)

- Investment feasibility study

2017

EuroChem,

NAK Azot,

Novomoskovsk,

Russia

Technological inspection of the prilling tower (complex fertilizers production plant, ammonium nitrate unit )

- Technical inspection

- Issuing recommendations and developing engineering solutions optimizing prilling tower technological mode.

2016

Azot, Kemerovo,

Russia

Complex technical inspection of urea production plant (Tecnimont technology)

- Technical inspection

- Development of engineering solutions optimizing technological processes, reducing energy consumption and enhancing reliability of unit operation

- Investment evaluation

2015

EuroChem, NevAzot, Nevinnomyssk,

Russia

Technical inspection (urea plant № 2, urea units 1-3)

- Technical inspection

- Development of engineering solutions reducing energy consumption and increasing capacity

- Feasibility study

2015

Research Institute for Mineral Fertilizers (NIUIF), Moscow, Russia

Development of a reference guide on most appropriate technologies used to produce ammonia, mineral fertilizers and mineral acids (sections developed by NIIK: ammonia, NA, AN, CAN, urea, UAN). Scientific and technical support to get the approval of expertise.

2015

EuroChem, NevAzot , Nevinnomyssk,

Russia

Complex technical inspection (melamine\urea units №2a)

- Technical inspection

- Development of engineering solutions optimizing technological process during operation with melamine unit

2014

FNTC Group spol.s r.o,

Czesh Republic

Technical inspection of urea plant at FerganaAzot

- Technical inspection

2013

EuroChem, NAK Azot,

Novomoskovsk,

Russia

Technological inspection (urea plant №3, second line) aimed at capacity increase to 1600 t/d

- Technical inspection

2012

32,5% urea solution production unit (capacity 100000 TPY) including urea solution treatment unit on the basis of urea plant № 2 evaporation unit

- Urea units technical inspection considering the construction of a new unit

2011

Acron,

Veliky Novgorod,

Russia

Technical inspection of urea plant aimed at capacity increase and energy saving

- Technical inspection

2010-2011

PhosAgro,

Cherepovets,

Russia

Technological monitoring of urea unit performance in order to reduce ammonia consumption

- Technical inspection

2009

Severodonetsk Azot Association, Severodonetsk, Ukraine

Process monitoring of urea unit operation

- Technical inspection

- Recommendation issuing for capacity increase and energy saving

2008

Minudobreniya,

Perm,

Russia

Monitoring of urea production unit equipment

- Technical inspection

2006

Diagnostics & repair services

UralChem, Berezniki, Russia Replacement of nozzles Р1, Р2, Р3, Р4 Replacement of bottom liner Replacement of three liner belts in the reactor R-901 Revamps 2021
Azot, Kemerovo, Russia Replacement of nozzles Р1, Р2, Р3, Р4 Replacement of bottom liner in the reactor R-901 Revamps 2021
EuroChem, NAK Azot, Novomoskovsk, Russia Repair of three liner belts of cylindrical part of Urea Reactor pos. 11-R-1 Revamps 2021
Grodno Azot, Grodno, Belarus Relining of Urea reactor R-201, Urea-3 Revamps 2021
Grodno Azot, Grodno, Belarus Technical supervision of lining repair (urea synthesis unit pos. R-201, urea plant 4) - Repair works Under development
EuroChem, NevAzot, Nevinnomyssk, Russia Technical supervision of repair works (distillation column for heavy fractions pos.D-2203, №12А) - Repair works Under development
Repair of cylindrical section of the lining of synthesis reactor pos. 6/1 (urea plant 2) - Repair works 2020
Apatite, Volkhov, Russia Eddy-current testing of heat exchanger tubes (for equipment operating under excessive pressure) - Eddy-current testing 2019
EuroChem, NevAzot, Nevinnomyssk, Russia Corrosion and technical inspection of urea synthesis reactors pos. 6/1, 6/4, distillation columns pos. К-7/1, К-7/2, stripper-distillation units pos. Т8/1, 8/2, mixers pos. 5/1, 5/2, 5/3, 5/4, air heaters pos. 20/3 (urea unit №2А) Corrosion inspection 2019
MOPCO, Egypt Urea production unit MOPCO-2 corrosion inspection - Corrosion inspection 2019
Urea production unit MOPCO-3 corrosion inspection - Corrosion inspection 2019
Industrial group Phosphorite, Leningrad region, Кingisepp, Russia Eddy-current testing of heat recovery boiler and air heaters' heat- exchanger tubes - Eddy-current testing 2019
AlexFert, Egypt Recirculation heater internal surface heat exchanger tubes cleaning by thermo- pneumo-abrasive method - Repair works 2019
KuibyshevAzot, Togliatti, Russia Urea synthesis reactor pos. № 6/1 (№202КВ) repairing - Repair works 2019
EuroChem, NAK Azot, Novomoskovsk, Russia Corrosion and technical inspection of urea production unit 3 main equipment (line 1) - - Corrosion inspection 2019
Azot, Kemerovo, Russia Inspection and replacement of the urea synthesis reactor pos. R-901 lining (dome, cylindrical sections) - Repair works 2019
Grodno Azot, Grodno, Belarus Lining repair of synthesis reactor pos. R-201 urea plant №3 - Repair works 2019
«Meleuz mineral fertilizers», Meleuz, Russia Repair of heat exchanger tubes of evaporation unit pos. T-10 (ammonium nitrate production unit) - Repair works 2019
EuroChem, NevAzot, Nevinnomyssk, Russia Synthesis reactor relining (pos. 6/3, urea plant № 2) - Repair works 2019
Apatite, Cherepovets, Russia Eddy-current testing of pressure vessels' heat exchanger tubes - Eddy-current testing 2019
Nitrogénművek Zrt., Hungary Urea reactor R202 relining - Relining&repair 2018
Metafrax, Gubakha, Russia Casale SA, Switzerland Ammonia-urea-melamine complex - Technical assistance during commissioning and guarantee testing of the prilling tower - Field supervision 2018 to present
PG Phosphorite, Leningrad region, Kingisepp, Russia Eddy-current testing of heat recovery boiler tubes - Eddy-current testing
- Issuing recommendations for repairs
2018
TogliattiAzot, Togliatti, Russia Equipment corrosion and technical inspection (urea plant № 08К) - Corrosion inspection
- Developing recommendations for repairs
2018
UralChem, Berezniki, Russia Corrosion inspection - Corrosion inspection
- Developing recommendations for repairs
2018
Minudobreniya, Rossosh, Russia Eddy current testing - - Eddy current testing
- Developing recommendations for repairs
2018
EuroChem, NevAzot, Nevinnomyssk, Russia Corrosion and technical inspection of plant №2 - Corrosion inspection
- Developing recommendations for repairs
2018
KuibyshevAzot, Togliatti, Russia Relining of distillation column pos. K-7/2 of plant №4 - Repairs 2018
Grodno Azot, Grodno, Belarus Lining repair of synthesis reactor pos. R-201 urea plant №4 - Repairs 2018
TogliattiAzot, Togliatti, Russia Technical repairs manual - Developing recommendations for repairs 2018
Apatite, Cherepovets, Russia Replacement of mass-transfer trays in urea synthesis reactor pos. R-201 in urea plant №2 - Repair works

2018

Eddy-current testing of pressure vessels' heat exchanger tubes - Nondestructive testing
- Issuing recommendations for equipment operating and repairing

2018

Belenergomash, Belgorod, Russia Steel tubes samples intergranular corrosion testing - Testing2018
Apatite, Cherepovets, Russia Eddy-current testing of heat-exchanger tubes working under pressure. - Nondestructive testing
- Issuing recommendations for equipment operating and repairing
2018
EuroChem, NAK Azot, Novomoskovsk, Russia Corrosion and technical inspection of heat exchanger tubes of high pressure stripper pos. E-201 using eddy current method. - Corrosion and technical inspection
- Issuing recommendations for equipment operating and repairing
2017
EuroChem, NevAzot, Nevinnomyssk, Russia Cleaning heat exchangers pos. E-302 and E- 302B (urea production plant № 2А)- Nondestructive testing
- Equipment cleaning by thermo-pneumo- abrasive method
2017
Nitrogénművek Zrt., Pétfürdő Hungary  Corrosion and technical inspection of stripper pos. E-201 (urea production)- Nondestructive testing 2017
Cleaning heat exchanger tubes of stripper pos. E-201 (urea production)- Electro-hydro- mechanical cleaning of heat exchanger tubes2017

Nitrogénművek Zrt.,

Pétfürdő

Hungary

Corrosion and technical inspection of stripper pos. E-201 (urea production)

- Nondestructive testing –

- Electro-hydro- mechanical cleaning of heat exchanger tubes

2017

«Meleuz mineral fertilizers», Meleuz, Russia

Replacement of old tubes of evaporation unit (pos.Т-10, ammonium nitrate production unit)

- Nondestructive testing

- Development of repair method&technique

- Repair works

2017

EuroChem, NevAzot, Nevinnomyssk, Russia

Technical and corrosion inspection of urea synthesis reactors pos.6/1 and 6/3 (urea plant №2)

- Nondestructive testing

- Recommendations issue for equipment operating and repairing

2017

Minudobreniya,

Rossosh, Russia

Technical inspection of heat- exchanging tubes (plant АM-2)

- Nondestructive testing

- Recommendations issue for equipment repairing

2017

Grodno Azot,

Grodno,

Belarus

Repair of the lining of the synthesis reactor manhole (pos. R-201, urea plant №3)

- Technical documentation development

- Quality control of the works performed

2017

Technical and corrosion inspection of urea synthesis reactor pos. R-201 and HP condenser pos. E-202 (urea plant № 3)

- Inspection

- Issuing recommendations for repairing

2017

Technical and corrosion inspection of urea synthesis reactor pos. R-201, HP stripper pos. E-201 and HP condenser pos. E-202 (urea plant № 4)

- Inspection

- Issuing recommendations for repairing

2017

TogliattiAzot,

Togliatti, Russia

Inspection and development of recommendation for 14-R-1 synthesis reactor relining (urea production unit 08К)

- Nondestructive testing

- Issuing recommendations for repairing

2017

Kuibyshev Azot,

Togliatti,

Russia

Corrosion and technical inspection of the main technological equipment of urea production unit

- Nondestructive testing

- Issuing recommendations for repairing

2017

EuroChem, NevAzot, Nevinnomyssk,

Russia

Corrosion inspection and technical supervision of repair works on distillation column for heavy fractions (pos.D-2203, №12А)

- Nondestructive testing

- Recommendations’ issue for repairing

- Quality control of the works performed

2017

PhosAgro Cherepovets, Russia

Eddy-current testing of pressure vessels' heat exchanger tubes

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2017

ZNIGO,

Borisoglebsk, Voronezh region, Russia

Inspection of heat exchanger tubes of reflux condenser (urea production unit)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2017

Sorovskneft,

Tyumen,

Russia

Inspection of heat exchanger tubes of S&T oil heaters

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2016

EuroChem, NevAzot, Nevinnomyssk,

Russia

Inspection of heat exchanger tubes (urea plant 2A)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2016

Synthesis reactor dome relining (pos.6/1, plant №2)

- Development of repair method & technique

- Repair works

2016

Grodno Azot,

Grodno,

Belarus

Synthesis reactor relining on 2400 mm height (pos. R-201, Urea-3)

- Development of repair method &technique

- Repair works

2016

Technical and corrosion inspection of HP reactor pos. R-201, HP stripper pos. E-201(Urea-3)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2016

Egyptian Fertilizers Company (EFC), El Ain Sukhna,

Egypt

Relining of urea reactor 322-R-00 (Urea Plant EFC-1 Suez Fertilizers Co.)

- Inspection

- Development of repair method & technique

- Repair works

2016

UralChem,

Azot,

Berezniki,

Russia

Relining of urea synthesis reactor pos. R-901

- Development of repair method & technique

- Repair works

2016

EuroChem,

NAK Azot,

Novomoskovsk,

Russia

Corrosion and technical inspection of urea synthesis reactor pos. 6/1 (urea plant №2)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2016

Eddy-current testing of pressure vessels' heat exchanger tubes

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2016

PhosAgro Cherepovets, Russia

Eddy-current testing of heat- exchanger tubes of carbamate condenser pos. Е-202

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2016

«Meleuz mineral fertilizers», Meleuz, Russia

Replacement of old tubes of evaporation unit (pos.Т-10, ammonium nitrate production unit)

- Nondestructive testing

- Development of repair method &technique

- Repair works

2015

Grodno Azot, Grodno, Belarus

Corrosion and technical inspection of synthesis reactor pos.R-201, high-pressure scrubber pos. Е-203, high-pressure stripper pos. Е-201, high-pressure condenser pos.Е-202 (urea unit 3 and urea unit 4)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2015

Nitrogénművek Zrt.,

Pétfürdő

Hungary

Corrosion and technical inspection of stripper pos. E-201 (urea production)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2015

Azot, Cherkassy,

Ukraine

Development of technical documentation to replace three lining belts of cylindrical section of urea synthesis reactor.

- Technical documentation development

- Field supervision during manufacturing of equipment parts

2015

Minudobreniya,

Rossosh, Russia

Inspection of heat exchanging tubes of nitrous gases coolers (nitric acid production unit AK-72, the second stage)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2015

TogliattiAzot,

Togliatti,

Russia

Corrosion and technical inspection of the main technological equipment, pipelines and valves for urea plant №1,2

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2015

PhosAgro Cherepovets, Russia

Eddy-current testing of pressure vessels' heat exchanger tubes

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2015

DniproAZOT, Dneprodzerzhinsk,

Ukraine

Technical inspection of heat exchanger equipment (urea plant №1, urea plant №2)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2014

Grodno Azot,

Grodno,

Belarus

Corrosion inspection of HP urea synthesis reactor pos. R-201, HP stripper pos. E-201, HP scrubber pos. E-203 (urea plant №3)

HP stripper pos. E-201, HP condenser pos. E-202, additional heat exchanger section for preheater pos. E-302 (urea plant №4)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2014

Repair of two lining belts (urea synthesis reactor pos. R-201, urea plant №3)

- Technical documentation development

- Quality control of the works performed.

2014

Azot, Cherkassy,

Ukraine

Corrosion and technical inspection of gas pipelines, HP heat exchangers, tanks and vessels of plant M-6 (synthesis reactor pos. R-201, stripper pos. E-201, condenser pos. E-202, pipelines reg. No 481, 532, 534, 535)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2014

Inspection of heating chamber exchanging tubes (evaporation unit pos. 5/1 and 5/2, plant M-9)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2014

DniproAZOT

Dneprodzerzhinsk,

Ukraine

Corrosion and technical inspection of lining and internal devices (reactor, stripper, condenser, scrubber) for urea plant № 1 and urea plant № 2.

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2014

Kuibyshev Azot,

Togliatti,

Russia

Corrosion and technical inspection of main equipment for urea plant № 4

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2014

EuroChem,

NAK Azot,

Novomoskovsk,

Russia

Corrosion inspection of heat exchange equipment (urea plant №3 (line 2)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2014

Severodonetsk Azot Association,

Severodonetsk,

Ukraine

Corrosion and technical inspection of synthesis reactors internal surface (urea plant M-3)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

Azot, Cherkassy,

Ukraine

Inspection and surveying of reformer and heat exchanger equipment for plant A-5

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

Grodno Azot,

Grodno,

Belarus

Corrosion inspection of urea synthesis reactor for urea plant № 4.

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

Technical inspection of urea synthesis reactor and HP condenser for urea plant № 3

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

Azot, Kemerovo,

Russia

Synthesis reactor repair support services

- Technical documentation development

- Technical inspection

- Quality control of the works performed

2013

PhosAgro Cherepovets, Russia

Eddy-current testing of pressure vessels' heat exchanger tubes

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

EuroChem,

NAK Azot,

Novomoskovsk,

Russia

Corrosion and technical inspection of main technological equipment (urea plant №3 (first line)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

Acron,

Veliky Novgorod,

Russia

Inspection of heat exchanging tubes of condenser pos. Т-506 (urea unit № 5).

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

Corrosion and technical inspection of urea synthesis reactor K-501 (urea unit № 5)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

EuroChem, NevAzot,

Nevinnomyssk,

Russia

Corrosion inspection using eddy current testing of equipment (plant № 2А, 12А)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

AB Achema,

Lithuania

Corrosion inspection of urea synthesis reactor (Ø1600mm) and HP mixer.

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

FNTC Group spol.s r.o,

Czesh Republic

Corrosion and technical inspection of urea plant, ammonium nitrate and nitric acid units for FerganaAzot

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

Azot, Cherkassy,

Ukraine

Corrosion and technical inspection of equipment (urea plant M-2)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

Grodno Azot,

Grodno, Belarus

Inspection of absorber ferromagnetic heat exchanger tubes (ammonia plant № 4)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2013

Razi Petrochemical Company

Iran

Corrosion inspection of urea plant equipment

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2012-2013

Acron,

Veliky Novgorod,

Russia

Corrosion and technical inspection of distillation column pos. 7/2 (urea plant)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2012

Salavat Neftekhimremstroy, Salavat,

Russia

Repair of urea synthesis reactor pos. 6-1, 6-2 (Gas and Chemical plant «Gasprom nephtehim Salavat», plant № 50)

- Corrosion and technical inspection

- Repair works

- Quality control of the works performed

2012

Grodno Azot, Grodno, Belarus

Heat- exchanger tubes inspection (HP equipment of urea plant №3)

- Nondestructive testing

2012

Azot, Cherkassy,

Ukraine

Ferromagnetic heat- exchanger tubes inspection (pos. 1140-C, ammonia plant A-5)

- Nondestructive testing

2012

Corrosion and technical inspection of equipment (urea plant M-6)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2012

Azot, Kemerovo,

Russia

Emergency repair of the lining of synthesis reactor pos.R-901 (urea plant).

- Location of the defect

- Reactor body repairing

- Quality control of the works performed

2012

EuroChem, NevAzot,

Nevinnomyssk,

Russia

Corrosion and technical inspection of equipment (urea plant №2)

- Nondestructive testing

- Issuing recommendations for equipment operating and repairing

2012

Concern Stirol,

Gorlovka,

Ukraine

Complex repair of synthesis reactor pos. R-901 (urea plant, location1)

- Technical documentation development

- Repair works

- Technical inspection of the works performed.

2012-2013

Concern Stirol,

Gorlovka,

Ukraine

Emergency repairing of synthesis reactor pos. R-901 (urea plant, location 1)

- Location of the defect

- Reactor body repairing

- Technical inspection of the works performed

2012-2013

EuroChem,

NAK Azot,

Novomoskovsk,

Russia

Corrosion and technical inspection of critical equipment (urea plant № 3, second line)

- Nondestructive testing

2012

Acron,

Veliky Novgorod,

Russia

Lining replacement of synthesis reactor pos. 6/4 (urea plant)

- Technical documentation development

- Technical inspection

- Quality control of the works performed

2012-2013

UralChem,

Azot, Berezniki,

Russia

Repair of cylindrical section of the lining of synthesis reactor pos. R-901 (urea plant).

- Corrosion and technical inspection of lining

- Technical documentation development

- Technical inspection

- Quality control of the works performed.

2012

Gazprom Neftekhim Salavat

Salavat,

Russia

Lining replacement of the bottom parts of urea synthesis and distillation column (urea plant №50)

- Technical documentation development

2012

Agro-Cherepovets, Cherepovets,

Russia

Corrosion and technical inspection of critical equipment (urea plant).

- Corrosion and technical inspection of lining using NDT

- recommendation issue for equipment operating and repairing

2012

Azot,

Kemerovo,

Russia

Emergency repairing of the heat exchanger cover pos. E-902 (urea plant)

- Location of the defect

- Repair support services

2012

Togliattiazot,

Togliatti, Russia

Repair of the lining of HP stripper of urea plant

- Location of the defect

- Repair support services

2012

Gazprom Neftekhim Salavat,

Salavat,

Russia

Emergency repairing of synthesis reactor 6/1 (urea plant №50).

- Location of the defect

- Repair support services

2011

EuroChem, NAK Azot,

Novomoskovsk,

Russia

Corrosion and technical inspection of critical equipment (urea plant № 3, first line)

- Inspection

2011

Odessa Port Plant,

Yuzhny,

Ukraine

Corrosion and technical inspection of high pressure equipment (urea plant № 2)

- Inspection

2011

Acron, Veliky Novgorod, Russia

Corrosion and technical inspection of urea synthesis reactor (urea plant № 5)

- Inspection

2011-2012

UralChem,

Azot, Berezniki,

Russia

Repair of the lining of urea unit synthesis reactor

- Location of the defect

- Repair support services

2011

EuroChem, NevAzot,

Nevinnomyssk,

Russia

Repair of two lining belts in urea reactor (urea plant 2А)

- Technical documentation development

- Repairing works assistance

- Quality control of the works performed

2011

PhosAgro, Cherepovets, Russia

Cleaning of heat exchanging equipment of evaporation unit (first stage)

- Removing scales from evaporating unit (first stage) tubes by thermo-pneumo-abrasive method

2011

Acron,

Veliky Novgorod,

Russia

Technical guidance for relining of urea synthesis reactor pos. 6/2 of urea plant

- Technical documentation development

- Repairing works assistance

- Quality control of the works performed

2011

EuroChem, NevAzot, Nevinnomyssk,

Russia

Corrosion and technical inspection of equipment (plants №2, №2А)

- Inspection

2011

DniproAZOT

Dneprodzerzhinsk,

Ukraine

Corrosion and technical inspection of equipment (urea plant№1 and urea plant №2)

- Nondestructive testing

- Recommendation issue for equipment operating and repairing

2011-2012

Concern Stirol,

Gorlovka,

Ukraine

Corrosion and technical inspection of sections №1 and №2 (urea plant)

- Inspection

2011

Odessa Port Plant,

Yuzhny,

Ukraine

Corrosion and technical inspection of equipment (urea units №1and № 2)

- Inspection

2010

EuroChem, NevAzot, Nevinnomyssk,

Russia

Corrosion and technical inspection of equipment (urea plant №2)

- Inspection

2010

Technical guidance for partial relining of synthesis reactor 6/3

- Technical documentation development

- Technical guidance of repair works

2010

Acron,

Veliky Novgorod,

Russia

Corrosion inspection of urea synthesis reactor 6/2

- Inspection

2010

Industrial safety expertise

- Diagnostics of urea synthesis reactor 6/1 and 6/4

2010

Cleaning of heat exchanging equipment of MP distillation

- Removing scales from heat exchanging tubes by pneumocurrent method

2010

Azot, Cherkassy,

Ukraine

Corrosion inspection of equipment (urea plant M-2 and M-6)

- Inspection

2010

Relining of upper part of urea synthesis reactor (plant M-2)

- Development of technical documentation

- Repair works

- Quality control of the works performed

2010

PhosAgro, Cherepovets, Russia

Corrosion and technical inspection of urea plant equipment

- Nondestructive testing

2010

DniproAzot, Dneprodzerzhinsk,

Ukraine

Corrosion and technical inspection of equipment (urea plant №1 and urea plant № 2)

- Inspection

2010

EuroChem, NAK Azot, Novomoskovsk,

Russia

Technical guidance of partial relining of synthesis reactor 6/2

- Technical documentation development

- Repairing works assistance

- Quality control of the works performed

2010

Azot, Kemerovo, Russia

Corrosion inspection of urea synthesis reactor

- Inspection

2010

EuroChem, NevAzot , Nevinnomyssk,

Russia

Corrosion and technical inspection (urea units №2 and №2a)

- Inspection

2009

Industrial safety expertise of technical devices (urea plant №2)

- Corrosion and technical inspection

2008

EuroChem, NAK Azot, Novomoskovsk,

Russia

Repair of the lining of synthesis reactor, separator and stripper (urea plant №3)

- Technical assistance

2008

Azot,

Kemerovo,

Russia

Repair of urea synthesis reactor

- Development of technical documentation and technical guidance for urea synthesis reactors repair

2008

DniproAzot,

Dneprodzerzhinsk,

Ukraine

Industrial safety expertise of technical means

- Corrosion and technical inspection

2008

R&D Institute of Measurement Systems,

Nizhny Novgorod,

Russia

Process diagnostic to determine the remaining service life of equipment and pipelines of treatment plants.

- Inspection

2007

Rikor Electronics, Arzamas, Russia

Industrial safety expertise of technical means

- Equipment diagnostics

2007

PhosAgro, Cherepovets, Russia

Industrial safety expertise of pressurized vessels (urea plant)

- Equipment diagnostic and expert conclusion for service life extension of equipment

2007

EuroChem, NevAzot, Nevinnomyssk,

Russia

Repair of two lining belts (urea reactor)

- Development of technical documentation

- Supervising manufacturing of the material

- Technical assistance

- Field supervision

2007

EuroChem, NAK Azot, Novomoskovsk,

Russia

Inspection of stripper tubes by eddy-current method

- Inspection

2007

Corrosion inspection of stripper

- Inspection

2007

FerghanaAzot,

Uzbekistan

Corrosion inspection of critical vessels and pipelines (urea plant)

- Inspection

2007

DniproAzot,

Dneprodzerzhinsk,

Ukraine

Corrosion and technical inspection of HP reactor, stripper, condenser (plant №2)

- Inspection

- Repair procedure development

- Repair works

2007

Equipment procurement

For production complexes

Metafrax, Gubakha, Russia

Ammonia-urea-melamine complex

- Equipment procurement for OSBL facilities

2016-to present

Metafrax, Gubakha, Russia

Casale SA, Switzerland

Ammonia-urea-melamine complex

- Equipment procurement for prilling tower construction

Ammoni,

Mendeleevsk,

Russia

Ammonia- methanol- urea complex

- Equipment procurement for OSBL facilities

2010-2015

For ammonia production units

PhosAgro,

Cherepovets,

Russia

Ammonia production unit AM-3 (capacity 2200 TPD)

- Equipment procurement for analytical laboratory

2016-2017

For urea production units

Not disclosed (Confidential Information) UAN production unit - Package procurement Under development
Not disclosed (Confidential Information) UAN production unit - Equipment procurement (vortex mixer) Under development
Not disclosed (Confidential Information) Urea production unit Critical equipment procurement for urea unit modernization project Under development
Acron, Veliky Novgorod, Russia Urea production unit №6 construction with capacity 600 TPD- Equipment procurementUnder development
Rashtriya Chemicals and Fertilizers Ltd., Mumbai, IndiaUrea units modernization (Thal)- Procurement & installation of three sets of Internal Devices Under development
Gujarat Narmada Valley Fertilizers & Chemicals Ltd, IndiaUrea unit modernization - Procurement & installation of vortex mixer into urea synthesis reactor2017

Rashtriya Chemicals and Fertilizers Ltd., Mumbai, India

Urea units modernization (Thal)

- Procurement & installation of three Sets of Internal Devices

Under development

KuibyshevAzot, Togliatti, Russia

Technical modernization of urea unit № 4 (evaporation, hydrolysis and desorption sections)

- Equipment procurement

2016-2017

Rashtriya Chemicals and Fertilizers Ltd., Mumbai, India

Trombay V urea plant modernization

- Procurement & installation of a Set of Internal Devices comprising Vortex Mixer and Conversion Booster for urea synthesis reactor

2015 -2016

Casale SA, Switzerland

Urea production unit and new prilling tower construction (capacity 2200 TPD) at TogliattyAzot site

- Equipment procurement for prilling tower and new urea reactor support facilities.

2015-to present

EuroChem,

NAK Azot,

Novomoskovsk,

Russia

Revamp of urea unit 2 (gas vent elimination)

- Equipment procurement

2012-2015

PhosAgro- Cherepovets, Cherepovets, Russia

Urea production plant (section № 2) technical modernization with capacity increase to 1600 TPD

- Supervising equipment manufacturing

2014-2016

EuroChem, NAK Azot,

Novomoskovsk,

Russia

Technical modernization of the urea production plant №2

- Equipment procurement

2013-2016

32,5% urea solution production unit (capacity 100000 TPY) including urea solution treatment unit on the basis of urea plant № 2 evaporation unit

- Equipment procurement

2013-2015

Nagarjuna Fertilizers and Chemicals Limited,

India

Urea synthesis unit № 2 modernization

- Procurement & installation of vortex mixer into urea synthesis reactor

2013

Acron,

Veliky Novgorod,

Russia

Urea production units (1-4) revamping aimed to capacity increase up to 2000 TPD and feedstock/energy saving

- Equipment procurement

2016

Azot, Cherkassy,

Ukraine

Design and procurement of HP stripper pos. E-201 with capacity increase up to 1500 tpd (urea plants M-2)

- HP stripper design and procurement

2011-2012

Azot,

Kemerovo,

Russia

Urea production unit revamping with high speed drum granulator installation

- Equipment procurement

2011-2013

Acron,

Veliky Novgorod,

Russia

Evaporation system for urea production unit and prilling tower modernization with capacity increase

- Equipment procurement

2011-2013

Maxam-Chirchik,

Chirchik,

Uzbekistan

Modernization and technical upgrading of urea unit

- Equipment procurement

- Commissioning

2010-2012

UralChem,

Azot, Berezniki,

Russia

Urea synthesis reactor modernization

- Set of Internal Devices procurement

- Field supervision

2010

Salavatnefteorgsintez

Salavat, Russia

Prilling towers’ modernization for urea plant №24

- Equipment procurement

- Commissioning

2009-2010

PhosAgro Cherepovets,

Russia

Prilling tower for urea production (capacity of 1500 TPD)

- Equipment procurement

2008-2012

Acron,

Veliky Novgorod,

Russia

Urea unit №5 on the basis of relocated unit

- Equipment procurement

2007–2011

EuroChem,

NAK Azot, Novomoskovsk,

Russia

Revamp of urea plant №3 with capacity increase to 2000 TPD

- Material procurement

2007–2010

Severodonetsk Azot Association, Severodonetsk, Ukraine

Urea unit revamp with capacity increase from 1200 up to 1500 TPD

- Equipment procurement

2007–2010

EuroChem, NevAzot ,

Nevinnomyssk,

Russia

Urea evaporation unit for melamine plant

- Equipment procurement

2008 – 2010

KuibyshevAzot,

Togliatti,

Russia

Revamp of urea unit with capacity increase

- Equipment procurement

- Field supervision

2007–2008

Severodonetsk Azot Association,

Severodonetsk,

Ukraine

Urea unit revamp with capacity increase from 1000 up to 1200 TPD

- Equipment procurement

2006-2007

PhosAgro,

Cherepovets,

Russia

Revamping of distillation unit with capacity increase (urea production plant)

- Equipment procurement

2007

Salavatnefteorgsintez

Salavat, Russia

Revamping of urea plant №50

- Equipment procurement

2006 –2008

Azot, Kemerovo,

Russia

Revamp of urea synthesis unit

- Procurement of internals into reactor pos. R-101

2006

Grodno Azot, Grodno, Belarus

Revamp of urea production unit, installation of recuperator

- Equipment procurement

- Field supervision

2006

Acron,

Veliky Novgorod,

Russia

Installation of the 5th urea synthesis reactor

- Equipment procurement

2006

NevAzot,

Nevinnomyssk,

Russia

Revamping of urea production plant №2

- Equipment procurement

- Field supervision

2006

Azot, Kemerovo,

Russia

Revamp of urea synthesis unit

- Procurement of internals into reactor pos. R-101

- Field supervision

2006

For ammonia nitrate production unit

KazAzot,

Aktau,

Kazakhstan

Ammonia nitrate production unit modernization: HSDG for ammonia nitrate manufacturing

- Equipment procurement

2011-2012

For warehouses

Pervouralsky novotrubny works, Perovuralsk,

Russia

Revamp of liquid ammonia storage unit № 33

- Equipment procurement

2006-2007

Zawolzhsky Motorny Zawod,

Zavolshye,

Russia

Revamp of sulphuric acid storage unit

- Turnkey project

2006-2007

Petrol storage unit

- Turnkey project

2006

Nizhegorodsky machine-building plant,

Russia

Revamping of chlorine storage unit and chlorinator

- Turnkey project

2006-2007

For other facilities

Not disclosed (Confidential information) Installation of the hydro foamy filtration system (wet scrubbing) - Equipment procurement 2019

QAFCO (Qatar Fertilizer Company),

Qatar

Multipurpose High Speed Drum Granulation (HSDG) Pilot Plant for production of Granulated Urea with additives, capacity 100 kg per hour

- Equipment procurement

- Field supervision,

- Commissioning

2014-2015

PVFCCо,

Phu My I,

Ba Ria Vung Tau,

Vietnam

HSDG unit for production of compound fertilizers (capacity 100 kg/h)

- Equipment procurement

- Field supervision

- Commissioning

2014-2015

Zawolzhsky Motorny Zawod,

Zavolshye,

Russia

Project development and construction of testing station for diesel engines

- Turnkey project

2009

For equipment repairing

EuroChem, NevAzot, Nevinnomyssk, Russia Repair of cylindrical section of the lining of synthesis reactor pos. 6/1 (urea plant 2) - Equipment procurement Under development

Meleuz mineral fertilizers, Meleuz, Russia

Replacement of old tubes of evaporation unit (pos.Т-10, ammonium nitrate production unit AS-72М)

- Metal structures procurement for repairing works

2017

Grodno Azot, Grodno, Belarus

Repair of the lining of the synthesis reactor manhole (pos. R-201, urea plant №3)

- Metal structures procurement for repairing works

2017

Egyptian Fertilizers Company (EFC), El Ain Sukhna,

Egypt

Relining of urea reactor 322-R-00 (Urea Plant EFC-1 Suez Fertilizers Co.)

- Metal structures procurement for repairing works

2016

Meleuz mineral fertilizers, Meleuz, Russia

Replacement of old tubes of evaporation unit (pos.Т-10, ammonium nitrate production unit)

- Equipment procurement

2015

Grodno Azot, Grodno, Belarus

Repair of two lining belts (urea synthesis reactor pos. R-201, urea plant №3)

- Metal structures procurement for repairing works

2014

Corrosion inspection of urea synthesis reactor (urea plant №4)

- Metal structures procurement for repairing works

2013

Azot, Kemerovo,

Russia

Synthesis reactor repair support services

- Metal structures procurement for repairing works

2013

Concern Stirol,

Gorlovka,

Ukraine

Complex repair of synthesis reactor pos. R-901 (urea plant, location1)

- Metal structures procurement for repairing works

2012-2013

Acron,

Veliky Novgorod,

Russia

Lining replacement of synthesis reactor pos. 6/4 (urea plant)

- Metal structures procurement for repairing works

2012-2013

UralChem,

Azot, Berezniki,

Russia

Repair of cylindrical section of the lining of synthesis reactor pos. R-901 (urea plant)

- Metal structures procurement for repairing works

2012

EuroChem, NevAzot,

Nevinnomyssk,

Russia

Repair of two lining belts in urea reactor (urea plant 2А)

- Metal structures procurement for repairing works

2011

Acron,

Veliky Novgorod, Russia

Set of internal devices installation into urea plant reactor №5

- Metal structures procurement for repairing works

2011

Technical guidance for relining of urea synthesis reactor pos. 6/2 of urea plant

- Metal structures procurement for repairing works

2011

Azot, Cherkassy,

Ukraine

Relining of upper part of urea synthesis reactor (plant M-2)

- Metal structures procurement for repairing works

2010

EuroChem, NAK Azot, Novomoskovsk,

Russia

Technical guidance of partial relining of synthesis reactor 6/2

- Metal structures procurement for repairing works

2010

EuroChem, NevAzot, Nevinnomyssk,

Russia

Repair of two lining belts (urea reactor)

- Supervising manufacturing of material

2007

Kuibyshev Azot, Togliatti, Russia

Revamping of urea storage unit

- Field supervision

- Commissioning works

2007

Fertalge Industries SPA,

Algeria

Prilling tower for urea production

- Field supervision

2002-2005