02/15/2013
Сonstruction of new ammonia- methanol- urea complex in Mendeleevsk (Tatarstan) is being continued
During the first phase the following works were carried out: land leveling, connecting passages and perimeter fencing installation. Video surveillance and access control system were assembled and lighting system was provided. Water and sewage pipelines as well as off sites water supply utilities are being constructed.
New production buildings begin to appear. The foundations for 16 buildings were being laid. Old walls were dismantled and sandwich panels were installed for administration and laboratory buildings 302 and 201. Inside wall building and window installation have begun. Monolithique framework laying, setting of internal and external walls is being completed in the main administrative building.
As we have already mentioned JSC NIIK is performing functions of general designer and contractor in the project.