JSC NIIK signed a contract with JSC Azot (Kemerovo) for technical revamping of urea production unit

The successful execution of the project aimed to remodel urea synthesis unit in the urea production complex with a new-designed vortex mixture installation in the synthesis column has already demonstrated that NIIK? s technology allows to achieve the maximum impact for minimum cost.
Considering this positive experience JSC Azot has signed a contract for existing urea production unit modernization providing some stability to the growth rate of output (1700 tons per day) and decreasing energy consumption. The urea quality will be also improved with the use of high speed drum granulators, which is also the development of our Institute.
The project will be conducted in two steps, the first is scheduled to be released in 2012