The first phase of works aimed at the construction of CJSC «Korund - Cyan» was completed

In December 2011 JSC NIIK has issued the first part of the detail design documentation package for the construction of the sodium cyanide production plant with the capacity 40000 mt a year.

The complex of works to prepare basic design documentation for the modernization and construction of the sodium cyanide production plant with the capacity 80000 mt a year for the JSC Korund-cyan has been carried out by NIIK company and positive reply and approval for this construction project was received by the evaluation of RF State Expert Department of Moscow on February 2011.

The civil engineering section of the project was carried out entirely by NIIK company: sodium cyanide synthesis reactor vessel, administration and on- site facilities, ammonia and alkali storage units, unloading racks for liquid ammonia receiving operations, exhaust gases burning installation, finished products storage area, closed looped cooling towers, steam, nitrogen and feed water generation units, industrial waste water treatment system, heating water production unit, electric power plants and many others. Some workspace improvements as well as the garage, workhouses intrashop and intershop racks were designed.

The engineering tasks were performed in accordance with technical solutions of the basic project of «EPC» company, responsible for technological part of the project, electrical and automatic control systems.
The first step provides the capacity of 40000 mt a year, the second will double this figure and is expected to bring the total capacity of 80000 mt a year. JSC NIIK will take responsibility for the engineering performance of the second phase. The works are scheduled to start around February 2012.